Logo Zephyrnet

Equinox Gold công bố nghiên cứu tiền khả thi tích cực về việc mở rộng Aurizona và tăng 73% đối với trữ lượng khoáng sản

Ngày:

Updated Mineral Reserve and Resource estimates for Aurizona, incorporating the new underground and open-pit deposits and offsetting 18 months of mining depletion, show a 73% increase over the 31 Tháng mười hai, 2019 estimate with 1.7 million oz of Proven & Probable Mineral Reserves grading 1.60 grams per tonne (“g/t”) gold plus 868,000 oz of Measured & Indicated Mineral Resources (exclusive of Reserves) grading 1.49 g/t gold.

AURIZONA EXPANSION HIGHLIGHTS

  • NPV sau thuế5% of $ 314 triệu at $1,500/oz gold and $ 600 triệu at $1,800/oz gold
  • $ 464 triệu after-tax LOM cumulative net cash flow at $1,500/oz gold and $ 830 triệu at $1,800/oz gold
  • $803/oz average LOM cash costs
  • $944/oz AISC trung bình từ năm 2024 trở đi và $1,058/oz trung bình AISC LOM
  • 1.5 million oz LOM gold production at an average recovery of 90.5%
    • More than 160,000 oz peak average annual gold production from 2026 to 2029
    • 137,000 oz average annual gold production (LOM)
  • 1.7 million oz Proven & Probable Mineral Reserves grading 1.60 g/t gold
  • $ 154 triệu underground mine initial capital costs, including $ 20 triệu dự phòng
  • 11-year mine life with additional expansion potential from further exploration success

Christian Milau, CEO of Equinox Gold, stated: “Incorporating the Aurizona underground and satellite deposits into our mine plan will nearly double the Aurizona mine life, increase annual production and generate almost $1 billion of net cash flow at current gold prices. I am incredibly proud of what our team has accomplished at Aurizona. The expansion will create additional economic and social opportunities for our community partners and substantial value for our shareholders, with significant potential for further growth as we continue to explore what could eventually be a multi-decade mine.”

Scott Heffernan, EVP Exploration of Equinox Gold, stated: “Exploration continues to unlock the potential at Aurizona. We have successfully replaced reserves from nearly three years of mining and provided an additional 70% growth of both mineral reserves and mineral resources. We expect to demonstrate additional growth at Aurizona with ongoing exploration focused on mine life extension through infill drilling and conversion of resources to reserves, plus significant near-mine, underground and regional exploration to further develop this mining district as a cornerstone asset for Equinox Gold.”

TỔNG QUAN

Equinox Gold achieved commercial production at Aurizona in 2019 Tháng Bảy after constructing a new mill and upgrading existing infrastructure. With an initial capital spend of only $ 160 triệu, Aurizona has produced more than 260,000 oz of gold and generated more than $ 190 triệu in free cash flow since commencing production.

The Piaba gold deposit contains gold mineralization in a vein system that extends at least four kilometres (“km”) along strike with smaller satellite deposits to the east and west of the main Piaba deposit. Recent drilling has shown that gold mineralization also extends below the ultimate open pit to depths greater than 1,000 metres (“m”) from surface. In 2020, a total of 65 diamond drillholes totaling nearly 26,000 m were drilled in the underground deposit to support the PFS and underground resource estimate. Year to date, 30 drillholes totaling nearly 11,000 m have been drilled in the Piaba underground, Tatajuba and satellite deposits, the results of which will be incorporated into the next reserve and resource update.

Aurizona Overall Site Plan

The current operation consists of the Piaba open-pit mine and a conventional crushing and grinding circuit with an 8,000 tonnes-per-day (“t/d”) carbon-in-leach (“CIL”) plant. The expansion will incorporate ore from the existing Piaba open-pit deposit along with the Piaba underground deposit and the Tatajuba, Boa Esperança, and Genipapo open-pit deposits. While the expanded mine will continue to use the existing mill and surface infrastructure, the existing powerline will need to be upgraded and the mine will require additional tailings and waste rock storage. Mining and processing underground ore concurrently with open-pit ore will increase the average mill feed grade, increase annual gold production and extend the mine life to 11 years.

KHAI THÁC

The PFS considers the addition of an underground mine beneath the existing Piaba pit as well as the inclusion of two satellite open-pit areas: Tatajuba and Genipapo.

Khai thác mỏ ngầm

The underground mine will be developed along a total strike length of 2.3 km beneath the Piaba pit. Access to the mine will be via a ramp collared in hard rock within the pit. The currently defined seven separate mining areas will be accessed by a 2-km main haulage decline with separate internal ramps. The first 800 m of the main haulage will be developed as a single heading to the location of the primary ventilation raise, which also provides emergency egress. From that point onwards the ramp will be developed as a double ramp arrangement, with the second ramp used for ventilation purposes during production. All underground mine development is in stable rock units located on the hanging wall side of the mineralized body.

The proposed underground mining method is long-hole stoping due to good ground conditions and the steep dip of the deposit. The PFS contemplates owner mining of stopes and underground development. Most of the stopes will include permanent rib pillars and be backfilled with rockfill from underground development or open-pit waste. The addition of cement to rockfill is confined to higher-grade areas where mining recovery can be maximized by eliminating rib pillars and above sill pillars.

Ore release will occur early in underground development, and Equinox Gold is reviewing additional opportunities to access higher-grade zones earlier in the underground mining schedule to enhance economics. First ore is released after approximately two years with steady state production exceeding 3,300 t/d achieved by year four. This production level is maintained until the middle of year seven and then reduces until underground mining is complete at the end of year 10. The Crown Pillar between the Piaba open-pit and underground will be recovered when underground mining is complete. In the PFS mine plan, the underground deposit provides 6.5 million tonnes (“Mt”) of ore grading 2.77 g/t gold of fresh rock.

Aurizona Underground Development Plan (Isometric View Looking South)

Open-pit Mining

Open-pit mining is currently undertaken by a contractor using conventional drill and blast, load and haul methods.

Piaba and Piaba East are currently in production providing feed to the Aurizona mill. Piaba East is a single-phase pit that is expected to be depleted by the end of 2024. Piaba will continue until 2032, mining the remaining four phases in the design and also the crown pillar in the floor when underground mining is complete. In the PFS mine plan, Piaba provides 18.9 Mt grading 1.3 g/t gold with 83% of the feed material being fresh rock. Piaba East provides 1.2 Mt grading 1.46 g/t gold of primarily saprolite mill feed.

The Boa Esperança pit is scheduled to be mined and completed in 2021, providing a total of 0.9 Mt grading 0.81 g/t gold of saprolite mill feed and creating a freshwater storage facility for plant operations.

The Tatajuba deposit, located 4 km to the west of the Piaba pit, is a two-phase pit design scheduled to commence production in the fourth quarter of 2023. Mining would continue in 2024 then pause until 2027, when the second phase would be complete. In the PFS mine plan, Tatajuba provides 2.0 Mt grading 1.39 g/t gold with 70% of the material being saprolite and transition material and the remainder fresh rock.

The Genipapo area is located 3 km by road to the east of the Aurizona plant. This area is separated into two small areas called Genipapo North and Genipapo South that will share a common waste storage facility. Mining of Genipapo South would start in 2024 and then move to Genipapo North, which is completed in 2028. Combined, the two Genipapo pits are expected to provide 0.67 Mt grading 0.82 g/t gold of saprolite and laterite feed.

The Crown Pillar removal is expected to provide 1.9 Mt of fresh rock grading 1.36 g/t gold in 2031 and 2032, after underground mining is complete.

Aurizona Mine Plant Feed (LOM)

VỐN VÀ CHI PHÍ HOẠT ĐỘNG

The PFS contemplates a three-year capital development and construction timeline for the underground mine. Total initial capital costs during this period are estimated at $ 154 triệu. Underground capital costs assume the mining fleet is purchased. Leasing the mining fleet would reduce capital costs by $ 25 triệu.

Duy trì chi phí vốn của $ 383 triệu bao gồm $ 60 triệu for the underground mine, largely for continued capital development and equipment replacements and rebuilds, $ 79 triệu for open-pit capitalized stripping and $ 178 triệu for infrastructure. Infrastructure includes $ 98 triệu for the construction of additional tailings facilities, $ 22 triệu for powerline upgrades and a new substation, $ 26 triệu for building improvements, equipment, and automation, and $25 million for exploration.

Aurizona LOM Capital Costs

Mục

Ban đầu

($ M)

Duy trì
($ M)

Tổng số:

($ M)

Open-pit Mining


79

79

Khai thác mỏ ngầm

134

60

194

Chế biến


14

14

Cơ sở hạ tầng


178

178

môi trường


10

10

Dự phòng

20

43

63

Toàn bộ vốn

154

383

537

Aurizona Underground Capital Costs

Mục

Ban đầu

($ M)

Duy trì
($ M)

Tổng số:

($ M)

Underground Mine Capital Development

46

26

72

Thiết bị khai thác ngầm

34

24

58

Underground Mine Infrastructure

41

10

51

EPCM and Pre-production Costs

13

1

14

Dự phòng

20

9

29

Total Underground Mine Capital

154

69

224

Operating costs are estimated at $33.14 per tonne of ore processed, as summarized below. LOM average cash costs are estimated at $803/oz with LOM AISC estimated at $1,058/oz of gold sold. Following completion of significant sustaining capital expenditures, AISC from 2024 onward averages $944/oz.

Aurizona Operating Costs

Tổng chi phí hoạt động

Total LOM ($M)

$ / tấn

$ / oz

Open-pit Mining ($/t mined)


2.25


Open-pit Mining ($/t ore mined)


10.79


Underground Mining ($/t ore mined)


32.78


Khai thác mỏ

490

15.15

326

Mở hố

276

8.53

184

Underground

214

6.62

142

Chế biến

373

11.52

248

G&A

209

6.47

139

Tổng số:

1,072

$33.14

713

NHẠY CẢM KINH TẾ

Sử dụng giá vàng trường hợp cơ sở của $1,500/oz and incorporating only Proven & Probable Mineral Reserves, the Aurizona expansion has an after-tax NPV5% of $ 314 triệu and after-tax cumulative net cash flow of $ 464 triệu. Project economics are most sensitive to operating costs and changes in the gold price.

Aurizona Sensitivity to Gold Price

Giá vàng ($/oz)

$1,350

$1,500

$1,800

Net Cashflow (pre tax) ($M)

$295

$510

$941

Net Cashflow (after tax) ($M)

$249

$464

$829

NPV5% (pre tax) ($M)

$186

$354

$689

NPV5% (after tax) ($M)

$146

$314

$600

KHOÁNG SẢN & TÀI NGUYÊN

The expansion mine plan is based on Proven & Probable Mineral Reserves of 32.3 Mt grading 1.60 g/t gold for 1,660,000 contained oz of gold, an increase of 73% compared to the previously stated Mineral Reserves from 31 Tháng mười hai, 2019. Measured & Indicated Mineral Resources (exclusive of Mineral Reserves) are 18.1 Mt grading 1.49 g/t gold for 868,000 contained oz of gold, with additional Inferred Resources of 12.7 Mt grading 2.19 g/t gold for 895,000 contained oz of gold.

Aurizona Mineral Reserve Estimate
Ngày có hiệu lực 30 Tháng Sáu, 2021

Phân loại

Địa Chỉ

Tấn
(kt)

Hạng vàng
(g / t)

Chứa vàng
(koz)

Chứng minh

Piaba Open Pit

14,475

1.37

638


Piaba East Open Pit

828

1.59

42


Boa Esperança Open Pit

168

0.63

4


Piaba Underground

223

2.42

17


Crown Pillar 

638

1.54

32


Kho dự trữ   

249

0.92

7

Tổng số đã được chứng minh


16,581

1.39

740

chắc chắn

Piaba Open Pit

4,423

1.17

167


Piaba East Open Pit

414

1.22

16


Boa Esperança Open Pit

713

0.85

20


Tatajuba Open Pit

1,974

1.39

87


Genipapo Open Pit

673

0.81

18


Piaba Underground

6,305

2.77

562


Crown Pillar 

1,246

1.27

51

Tổng xác suất


15,749

1.82

920

Tổng số đã được chứng minh và có thể xảy ra

32,330

1.60

1,660

Notes: CIM Definition Standards (2014) were followed for calculating Mineral Reserves: This mineral reserve estimate is as of June 30, 2021 and is based on the mineral resource estimates for Piaba, Boa Esperança, Tatajuba, and Genipapo all dated June 30, 2021 by Equity Exploration. The mineral reserve calculation was completed under the supervision of Gordon Zurowski, P.Eng. of AGP., who is a Qualified Person as defined under NI 43-101. Mineral reserves are stated within the final design pits based on a $1,350/oz gold price. The gold cut-off grades used were: Piaba Open Pit – 0.35 g/t (laterite, saprolite, transition), 0.41 g/t (rock); Boa Esperança Open Pit – 0.36 g/t (laterite, saprolite); Tatajuba Open Pit – 0.43 g/t (laterite, saprolite, transition), 0.47 g/t (rock); Genipapo Open Pit – 0.36 g/t (laterite, saprolite); Piaba Underground – 1.80 g/t (rock); Open pit mining costs varied by area but averaged $2.25/t mined and included an extra $2/t for ore haulage to the process plant from Tatajuba. Underground Mining costs averaged $32.78/t ore mined. Processing costs averaged $11.52/t ore based on variable costs by material type of $7.84/t for laterite/saprolite, $8.08/t for transition and $12.63/t for fresh rock. G&A was $6.47/t ore processed. LOM average gold recovery is 90.5%. Numbers may not sum due to rounding.

Aurizona Mineral Resource Estimate (exclusive of Reserves)
Ngày có hiệu lực 30 Tháng Sáu, 2021

Phân loại

Địa Chỉ

Tấn
(kt)

Hạng vàng
(g / t)

Chứa vàng
(koz)

Đo

Piaba Open Pit

2,439

1.21

95


Boa Esperança Open Pit

66

0.60

1


Piaba Underground

1,000

2.10

67

Tổng đo được


3,505

1.44

163

Chỉ ra

Piaba Open Pit

3,114

1.19

121


Boa Esperança Open Pit

427

1.03

14


Tatajuba Open Pit

181

1.39

8


Genipapo Open Pit

249

0.84

7


Touro Open Pit

2,965

0.78

75


Piaba Underground

7,212

1.96

454


Tatajuba Underground

464

1.73

26

Tổng số được chỉ định


14,612

1.50

705

Tổng đo lường & chỉ định

18,117

1.49

868

Suy ra

12,689

2.19

895

Notes: Mineral Resource statement has been prepared in accordance with NI43-101 Standards of Disclosure for Mineral Projects (May 2016) and the CIM Definition Standards for Mineral Resources and Mineral Reserves (May 2014). Mineral Resources are reported exclusive of reserves. Mineral Resources are reported using a cut-off grade of 0.30 g/t gold for open pit resources and 1.00 g/t gold for underground resources. The Open Pit Mineral Resource is constrained using an optimized pit that has been generated using Lerchs-Grossman pit optimisation algorithm. The Underground Mineral Resources are constrained using a 1.00 g/t Au grade shell occurring the lower of 20m below the transition-fresh rock contact, or 20 m below the Reserve pit. Mineral Resources are based on the Mineral Resource statements for each respective deposit and area, and have been prepared by Trevor Rabb, P.Geo who is a qualified person as defined by National Instrument 43-101. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. Totals may not sum due to rounding.

LỊCH TRÌNH SẢN XUẤT

The Aurizona production schedule shows average annual production of 137,000 oz of gold during the 11-year mine life (from 2021 Tháng Bảy đến Tháng Sáu 2032) with average LOM AISC of $1,058/oz of gold sold. Total LOM production is estimated at 1,503,000 oz of gold with peak production in Years 2026 to 2029 averaging more than 160,000 oz per year at AISC of $970/oz vàng bán ra.

Aurizona Annual Gold Production and AISC

KIM LOẠI VÀ CHẾ BIẾN

The Aurizona process plant treats ore via a conventional cyanidation process. Run-of-mine (ROM) ore is processed using a conventional primary crush and SAG-Ball mill comminution circuit followed by a gravity circuit, CIL process and associated gold recovery and carbon handling circuits to produce gold doré. Combined recovery from gravity concentration and CIL is expected to average 90.5%. Recent metallurgical testwork on samples from Piaba underground and Tatajuba confirm a similar metallurgical response using the existing processing circuit. No flowsheet changes or plant modifications will be required to treat ore from future mining areas.

ĐIỆN

Currently the mine is serviced by a 69 kV powerline maintained by the regional utility CEMAR, with a substation at site. The current operation typically draws 10-11 MW of power from the grid. A total of 7 MW of additional power is required at peak running load for the underground mine expansion. A powerline upgrade is included in the PFS as well as a new surface substation. Diesel generators are also included for back-up emergency electrical power underground.

CHO PHÉP

The Economic Exploitation Plan (PAE) for Piaba, which was ratified in 2019, will be updated to include the Piaba underground mine operation before submission for approval from the Brazil National Mining Agency (ANM).

Equinox Gold received the Preliminary License (LP) for Tatajuba in Tháng Tám 2021 and anticipates receiving the Installation License (LI) in H1 2022, which will allow for the commencement of mine and infrastructure development.

Genipapo has an exploration permit under assessment by ANM. Upon ANM’s approval, Equinox Gold will submit a PAE requesting the Genipapo mining concession. Boa Esperança is fully permitted under the existing Piaba Operating License (LO).

ADDITIONAL OPPORTUNITIES & NEXT STEPS

An extensive exploration program is ongoing at Aurizona to further expand Mineral Resources, convert Resources to Mineral Reserves, and continue exploration along strike and at depth at a number of near-mine targets. There is potential to expand both the Piaba East and Boa Esperança open-pits, and the Piaba underground deposit remains open at depth and along strike. Numerous other near-mine targets including Micote, Mestre Chico, São Lourenço, Conceição and Ferradura all require further testing. In addition, gold mineralization at Tatajuba is yet to be fully defined and there is good potential that the Tatajuba deposit continues along strike and at depth, representing another opportunity for mine life extension with exploration success.

Equinox Gold plans to commence permitting of the exploration decline in late 2021, which will allow for targeted drilling of the ore body from underground and would also serve as the ramp for future underground mining.

CHUẨN BỊ BÁO CÁO KỸ THUẬT

Equinox Gold retained independent consultants to complete the PFS and prepare a technical report in compliance with National Instrument 43-101 (“NI 43-101”). Key aspects of the PFS include an updated underground mine design, revised Piaba pit design, inclusion of satellite Reserves and an update to the Mineral Resource and Mineral Reserve estimates, updated mine schedule, infrastructure development, and the supporting cost development with financial model. The findings and conclusions are based on information available at the time of preparation and data supplied by other consultants, as indicated in the report. The effective date of the PFS is 30 Tháng Sáu, 2021, đại diện cho ngày thông tin được sử dụng trong báo cáo kỹ thuật.

The Qualified Persons (“QPs”) are Gordon Zurowski, P.Eng. and Neil Lincoln, P.Eng. both of AGP Mining Consultants Inc. (“AGP”), and Eleanor đen, PGeo và Trevor Rabb, P.Geo, both of Equity Exploration Consultants Ltd. The Mineral Resources were prepared by Trevor Rabb based on the geological model prepared by Equinox Gold geologists, which Equity Exploration Consultants reviewed and verified when preparing the block model. The Mineral Reserves, mine plan and mining sections of the study were prepared by AGP with supervision by Gordon Zurowski. The PFS is being summarized into a technical report that will be filed within 45 days on the Company’s website at www.equinoxgold.com, trên SEDAR tại www.sedar.com và trên EDGAR tại www.sec.gov/edgar, in accordance with NI 43-101.

Để độc giả hiểu đầy đủ thông tin trong bản tin này, họ nên đọc toàn bộ báo cáo kỹ thuật khi có, bao gồm tất cả các tiêu chuẩn, giả định, loại trừ và rủi ro. Báo cáo kỹ thuật được thiết kế để đọc toàn bộ và các phần không nên được đọc hoặc dựa vào ngoài ngữ cảnh.

NGƯỜI ĐƯỢC ĐÁNH GIÁ

The technical content of this press release has been reviewed and approved by the QPs who were involved with preparation of the PFS: Gordon Zurowski, Eleanor đenTrevor Rabb.

Nội dung kỹ thuật của thông cáo báo chí này cũng đã được xem xét và phê duyệt bởi Doug Reddy, Msc., P.Geo., COO của Equinox Gold, Kevin Scott, P.Eng., Dự án VP của Equinox Gold, và Scott Heffernan, M.Sc., P.Geo., Equinox Gold’s EVP Exploration, all of whom are QPs under NI 43-101 for Equinox Gold.

GIỚI THIỆU VỀ EQUINOX GOLD

Equinox Gold is a Canadian mining company operating entirely in the Americas, with seven operating gold mines and a clear path to achieve one million ounces of annual gold production from a pipeline of development and expansion projects. Equinox Gold’s common shares are listed on the TSX and the NYSE American under the trading symbol EQX. Further information about Equinox Gold’s portfolio of assets and long-term growth strategy is available at www.equinoxgold.com hoặc qua email tại [email được bảo vệ].

LƯU Ý THẬN TRỌNG VÀ TUYÊN BỐ HƯỚNG TỚI

Lưu ý thận trọng cho độc giả Hoa Kỳ liên quan đến ước tính trữ lượng khoáng sản và tài nguyên khoáng sản

Information about mineral reserve and resource estimates in this news release has not been prepared in accordance with the requirements of U.S. securities laws. The technical information in this news release has been prepared in accordance with Canadian reporting standards and certain estimates are made in accordance with NI 43-101. NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for all public disclosure an issuer makes of technical information concerning mineral projects. Unless otherwise indicated, all mineral reserve and resource estimates contained in this news release have been prepared in accordance with NI 43-101 and the Canadian Institute of Mining, Metallurgy and Petroleum Definition Standards on Mineral Resources and Reserves (CIM Definition Standards). Canadian standards, including NI 43-101, differ significantly from the historical requirements of the Securities and Exchange Commission (the SEC), and mineral reserve and resource estimates contained in this news release, or incorporated by reference, may not be comparable to similar information disclosed by U.S. companies. The SEC has adopted amendments to its disclosure rules to modernize the mineral property disclosure requirements for issuers whose securities are registered with the SEC (the SEC Modernization Rules). The SEC Modernization Rules replace the historical property disclosure requirements for mining registrants that are included in SEC Industry Guide 7. U.S. companies must provide disclosure on mineral properties under the SEC Modernization Rules for fiscal years beginning 1 Tháng một, 2021 hoặc sau đó. Theo Quy tắc Hiện đại hóa của SEC, các định nghĩa về trữ lượng khoáng sản đã được chứng minh và trữ lượng khoáng sản có thể xảy ra đã được sửa đổi để tương tự về cơ bản với các Tiêu chuẩn Định nghĩa CIM tương ứng và SEC đã bổ sung các định nghĩa để nhận biết tài nguyên khoáng sản được đo lường, tài nguyên khoáng sản được chỉ định và tài nguyên khoáng sản được suy luận là về cơ bản cũng tương tự như các Tiêu chuẩn Định nghĩa CIM tương ứng; tuy nhiên, vẫn có sự khác biệt trong các định nghĩa và tiêu chuẩn theo Quy tắc Hiện đại hóa của SEC và Tiêu chuẩn Định nghĩa CIM. Do đó, trữ lượng và tài nguyên khoáng sản của Công ty được xác định theo NI 43-101 có thể khác biệt đáng kể so với khi chúng được xác định theo Quy tắc Hiện đại hóa của SEC.

Các biện pháp phi IFRS

Thông cáo báo chí này đề cập đến chi phí tiền mặt khai thác trên mỗi ounce được bán, chi phí duy trì tổng thể (“AISC”), chi phí vốn duy trì và mở rộng là các biện pháp không có ý nghĩa tiêu chuẩn hóa theo Chuẩn mực Báo cáo Tài chính Quốc tế (“IFRS”) và có thể không so sánh với các biện pháp tương tự được trình bày bởi các công ty khác. Việc đo lường và trình bày chúng nhằm mục đích cung cấp thông tin bổ sung và không nên được xem xét riêng lẻ hoặc thay thế cho các biện pháp đo lường hiệu suất được chuẩn bị theo IFRS. Các biện pháp không theo IFRS được sử dụng rộng rãi trong ngành khai thác mỏ để đo lường hiệu suất và Công ty tin rằng chúng mang lại sự minh bạch hơn nữa về chi phí liên quan đến sản xuất vàng và sẽ hỗ trợ các nhà phân tích, nhà đầu tư và các bên liên quan khác của Công ty đánh giá hiệu suất hoạt động, khả năng của nó để tạo ra dòng tiền tự do từ các hoạt động hiện tại và giá trị tổng thể của nó. Tham khảo phần “Các biện pháp không theo IFRS” trong phần Thảo luận và Phân tích của Ban Giám đốc Công ty cho giai đoạn kết thúc 31 Tháng mười hai, 2020, để thảo luận chi tiết hơn về các thước đo không theo IFRS này và cách tính toán của chúng.

Tuyên bố về phía trước

This news release contains certain forward-looking information and forward-looking statements within the meaning of applicable securities legislation and may include future-oriented financial information. Forward-looking statements and forward-looking information in this news release relate to, among other things: the Company’s ability to successfully advance the Aurizona expansion and achieve the results outlined in the PFS, the strategic vision for the Company and expectations regarding production capabilities and future financial or operating performance, the conversion of Mineral Resources to Mineral Reserves, and the Company’s ability to successfully advance its growth and development projects and anticipated benefits arising from the same, including the economic and social benefits and value for Equinox Gold shareholders expected from the Aurizona expansion. Forward-looking statements or information generally identified by the use of the words “will”, “expected”, “expect”, “anticipate”, “potential”, “estimate”, “opportunity”, “additional”, “could”, “eventually” and similar expressions and phrases or statements that certain actions, events or results “could”, “would” or “should”, or the negative connotation of such terms, are intended to identify forward-looking statements and information. Although the Company believes that the expectations reflected in such forward-looking statements and information are reasonable, undue reliance should not be placed on forward-looking statements since the Company can give no assurance that such expectations will prove to be correct. The Company has based these forward-looking statements and information on the Company’s current expectations and projections about future events and these assumptions include: prices for gold remaining as estimated; currency exchange rates remaining as estimated; exploration and development for the Aurizona expansion being completed as planned; tonnage of ore to be mined and processed; ore grades and recoveries; availability of funds for the Company’s projects and future cash requirements; capital, decommissioning and reclamation estimates; Aurizona Mineral Reserve and Mineral Resource estimates and the assumptions on which they are based; the estimated LOM for Aurizona; prices for energy inputs, labour, materials, supplies and services; no labour-related disruptions and no unplanned delays or interruptions in scheduled construction, development and production, including by blockade; all necessary permits, licenses and regulatory approvals are received in a timely manner; and the Company’s ability to comply with environmental, health and safety laws. While the Company considers these assumptions to be reasonable based on information currently available, they may prove to be incorrect. Accordingly, readers are cautioned not to put undue reliance on the forward-looking statements or information contained in this news release.

The Company cautions that forward-looking statements and information involve known and unknown risks, uncertainties and other factors that may cause actual results and developments to differ materially from those expressed or implied by such forward-looking statements and information contained in this news release and the Company has made assumptions and estimates based on or related to many of these factors. Such factors include, without limitation: fluctuations in gold prices; fluctuations in prices for energy inputs, labour, materials, supplies and services; fluctuations in currency markets; operational risks and hazards inherent with the business of mining (including environmental accidents and hazards, industrial accidents, equipment breakdown, unusual or unexpected geological or structural formations, cave-ins, flooding and severe weather); inadequate insurance, or inability to obtain insurance to cover these risks and hazards; employee relations; relationships with, and claims by, local communities and indigenous populations; the Company’s ability to obtain all necessary permits, licenses and regulatory approvals in a timely manner or at all; changes in laws, regulations and government practices, including environmental, export and import laws and regulations; legal restrictions relating to mining including those imposed in connection with COVID-19; risks relating to expropriation; increased competition in the mining industry; and those factors identified in the Company’s MD&A dated March 19, 2021 and its Annual Information Form dated 24 Tháng ba, 2021, cả hai đều liên quan đến năm kết thúc 31 Tháng mười hai, 2020và trong MD&A của Công ty đề ngày Tháng Tám 4, 2021 trong ba và sáu tháng đã kết thúc 30 Tháng Sáu, 2021, tất cả đều có sẵn trên SEDAR tại www.sedar.com và trên EDGAR tại www.sec.gov/ edgar. Các tuyên bố và thông tin hướng tới tương lai được thiết kế để giúp người đọc hiểu được quan điểm của ban lãnh đạo tại thời điểm đó đối với các sự kiện trong tương lai và chỉ phát biểu vào ngày chúng được đưa ra. Trừ khi được yêu cầu bởi luật hiện hành, Công ty không có nghĩa vụ thông báo công khai kết quả của bất kỳ thay đổi nào đối với bất kỳ tuyên bố hướng tới tương lai hoặc thông tin có hoặc được kết hợp bằng cách tham chiếu để phản ánh kết quả thực tế, các sự kiện hoặc phát triển trong tương lai, các thay đổi trong giả định hoặc các thay đổi khác các yếu tố ảnh hưởng đến các tuyên bố và thông tin hướng tới tương lai. Nếu Công ty cập nhật bất kỳ một hoặc nhiều tuyên bố hướng tới tương lai, không có suy luận nào cho thấy Công ty sẽ cập nhật bổ sung đối với những tuyên bố đó hoặc những tuyên bố hướng tới tương lai khác. Tất cả các tuyên bố hướng tới tương lai và thông tin có trong bản tin này được xác định rõ ràng là toàn bộ của chúng theo tuyên bố cảnh báo này.

NGUỒN Equinox Gold Corp.

PlatoAi. Web3 được mô phỏng lại. Khuếch đại dữ liệu thông minh.
Nhấn vào đây để truy cập.

Source: https://www.prnewswire.com:443/news-releases/equinox-gold-announces-positive-pre-feasibility-study-for-aurizona-expansion-and-73-increase-to-mineral-reserves-301380208.html

tại chỗ_img

Tin tức mới nhất

tại chỗ_img